Construction Progress of BT Projects to Dec 20, 2017

On the 2018 threshold, the BT projects on Thu Thiem New Urban Area still maintain their planned schedule. The 4 main roads’ unoccupied land have been completed and put into operation, including: section from the Embankment R2 - Nguyen Co Thach Street, section from Mai Chi Tho Boulevard to C4 intersection on R2, section from Saigon River Tunnel Park to C4 intersection on R3, and the entire R4. The remaining section stretches from Nguyen Co Thach Street to Mai Chi Tho Boulevard on R2 is scheduled to be put into use before the 2018 New Year.
Regarding Thu Thiem 2 Bridge, the following items have been implemented:
In District 2, soft soil treatment and infrastructure works have been completed. Roadworks is under construction, especially the approachment.
The main bridge deck: has its preparation work implemented, such as waterway traffic maintenance, temporary abutment, etc. for S2 pile drilling in Saigon River.
In District 1, bored piles of AS8 and N23 piers is completed which cross Metro route No.1. At the same time, the Urban Traffic Management Board No. 1 is relocating trees, carrying out the infrastructure in preparation for the ground handover to construct the Approachment by April 2018.
Following are some photos of the projects.

R1 – From C4 Intersection towards Bridge No. 14

R1 – From C1 Intersection towards C2 Intersection

R1 – C2 Intersection towards Lan Anh Village

R1 – C2 Intersection towards Bridge No. 6

R2 – Bridge No.10

R2 – From Bridge No.10 towards Mai Chi Tho Boulevard

R2 – C6 Intersection towards Bridge No.15

R3 – Bridge No.17

R3 – From Bridge No.17 towards Saigon River Tunnel

R4 – From Viaduct No.1 towards C4 Intersection

Thu Thiem 2 Bridge – Construction temporary abutment and bridge to construct S2 pile

News related

Construction progress of BT projects in Thu Thiem new urban area as of May 03, 2018
Construction progress of BT projects in Thu Thiem new urban area as of May 03, 2018

At present, BT projects in Thu Thiem New Urban Area meet the committed schedule. The unoccupied section of the 4 main roads has been completed in February 2017 in line with the BT contract and put into operation at locations connecting to the existing roads. Regarding the occupied section, Dai Quang Minh  waits or the city’s land handover for early completion and operation of the entire project.

In Thu Thiem 2 Bridge project, the Approach District 2 and District 1, S2 main Tower (in the middle of Saigon River) are implemented. Meanwhile, the ground clearance is awaited.
Construction Progress of BT Project as of May 20, 2017
Construction Progress of BT Project as of May 20, 2017
In 23rd April, 2017, a section of R2 route- from R2 Embankment to Nguyen Co Thach Street- was put into use by the Department of Transportation. Regarding the upcoming opening routes, Dai Quang Minh has finished constructing several bridges, including Bridge No.10, Bridge No.15, viaduct No.1, viaduct No.2, R2 Embankment; along with the section of R2 road that extends from Nguyễn Cơ Thạch Street to C4 Intersection; the section of R3 road that extends from Mai Chi Tho Street to C4 Intersection; and the section of R4 road that extends from C4 Intersection to Mai Chi Tho Street.
Construction Progress of BT Project as of Mar 31, 2017
Construction Progress of BT Project as of Mar 31, 2017

At the present, 4 main roads in Thu Thiem are entering its finishing stage and getting ready for the handover at the sections that have been fully acquired. Tree planting and traffic organization are carried out throughout the entire project. Below are the photos of Road R1 - Crescent Boulevard, Road R2 - Central Lake Drive, Road R3 - Saigon Riverside Road, and Road R4 - Delta Overpass.